Do you know of two methods for adding corrosion and scale inhibitors to boilers
Release time:
Aug 14,2024
Before adding the medicine, boil it in hot water at 60-70oC and filter it. The intermittent dosing method can be used, which means adding it once per shift or adding it all at once.
One type is a boiler with a water tank or pool, but without an economizer. The medicine can be directly added to the water tank or pool and fed into the furnace through the water supply system;
Another method is to use a dosing funnel to directly pour the medicine into the furnace.
Before adding the medicine, boil it in hot water at 60-70oC and filter it. The intermittent dosing method can be used, which means adding it once per shift or adding it all at once.
After adding chemicals, attention should be paid to controlling the boiler water indicators, with a pH value between 10-12 and a total alkalinity of 6-26mmol/L.
At the same time, regular discharge should be carried out with a discharge rate generally maintained between 5-10%, at least once per shift, and each time should not exceed 30-60 seconds. If there is no change in water level after discharge, check whether the old scale that has fallen off has blocked the pipeline. If the pipeline is blocked, timely measures should be taken.